1
1
1
2
3
4
5
6
7
8
9
10
April 2, 2026 : The Goods and Services Tax Appellate Tribunal (GSTAT), Principal Bench, has ruled that homebuyers are not entitled to any input tax credit (ITC) benefit where the entire real estate transaction from booking to construction and payment takes place after the introduction of the GST regime.
The decision came in DG Anti-Profiteering v. Sobha Limited (GSTAT Appeal No. 08 of 2025), where a single-member bench of Justice Mayank Kumar Jain upheld the closure report submitted by the Director General of Anti-Profiteering (DGAP) and found no violation of Section 171 of the Central Goods and Services Tax Act, 2017.
The dispute arose from a complaint by homebuyers in Sobha Limited’s “International City” project in Gurugram, alleging that the developer had failed to pass on ITC benefits by reducing prices after GST was introduced. The matter was referred for investigation, following which the DGAP examined the financial data and concluded that no additional ITC benefit had accrued to the developer.
As noted in the Tribunal record, the ratio of credit availed to purchase value actually declined from 12.26% in the pre-GST period to 11.02% in the post-GST period, reflecting a negative differential of 1.24%. This indicated that there was no incremental tax benefit requiring pass-through to buyers.
Before the Tribunal, Sobha Limited argued that all aspects of the transaction took place after GST came into force on July 1, 2017. The buyers had applied for allotment in June 2019, entered into a builder-buyer agreement in July 2019, and made all payments thereafter. Construction activity also commenced and concluded within the GST regime.
Accepting this position, the Tribunal held that Section 171 dealing with anti-profiteering primarily applies where there is a comparative benefit, such as a tax rate reduction or an increase in ITC, typically in projects spanning both pre-GST and post-GST periods. In a fully post-GST project, such a comparison does not arise.
The bench relied on the Delhi High Court’s ruling in Reckitt Benckiser India Pvt. Ltd. v. Union of India, reiterating that when both construction and supply occur entirely in the GST era, prices are presumed to have been fixed after factoring in available ITC. Therefore, no separate obligation exists to pass on additional benefits.
Importantly, the Tribunal clarified that the phrase “constructed in the post-GST period” does not require that the property be fully completed at the time of agreement. What matters is that the entire chain of events from booking and agreement to construction and payment falls within the GST regime.
On facts, the Tribunal found that these conditions were fully satisfied and that the complainants had not disputed the timeline of events. It also noted that the price of the unit had been agreed upon after factoring in GST and ITC benefits, and the buyers had accepted these terms at the time of entering into the agreement.
Concluding that no profiteering had occurred, the Tribunal upheld the DGAP’s report dated August 21, 2025, accepted the developer’s preliminary objections, and dismissed the proceedings.